Abstract:
During the procurement and installation of elevators, frequent problems occurred which delayed the completion of the elevator installation. The aim of the study is to analyze the dominant risk factors that influence the procurement and installation of elevators at PT. X which affects the time performance of elevator installation. Risk analysis was conducted based on PMBOK 2017, using the concept of probability and impact matrix. The risk factors identification process was performed using the literature study and archival analysis of PT X.